UDFS

Rookie,
NOM 11.05.2021 kl 08:38 6782

The main improvements and risk-reducing measures in the UDFS are:

· Reduced environmental footprint; 99% reduction in consumption of approved
chemicals in the production process (compared with the 2016 environmental
permit), around 80% reduction of CO2 emissions and approximately 40% reduction
of the process plant facilities footprint compared with the DFS

· Contract and execution strategy based on EPC partnerships and early vendor
engagement

· Stick-build construction methodology and improved ore flow logistics

· Reduced initial investment needed to realize the project from USD 311
million to USD 218 million, maintaining a Run-of-Mine (ROM) of 1.5 Mtpa

· Reduced process operating cost by more than 25% following from flowsheet
optimizations, including reduction in energy costs from use of electrical dryers
for drying of minerals

· Improved mining design for open pit and underground focusing on practical
and cost-effective operations. Mining schedule in open pit has been optimized
for the initial years and the underground mining schedule targets higher grades
and a simplified infrastructure

· Reduced market risk based on post-pandemic market forecasts for rutile and
garnet, retaining flexibility to increase garnet production in line with
increasing demand

· Attractive project economics with considerable reductions in market,
financing, and execution risks


Key economic figures:

·
· Pre-tax NPV@8% of USD 355 million
· Pre-tax IRR 22.5%
· Post-tax NPV@8% of USD 260 million
· Post-tax IRR 19.8%


· High-margin cash flow and short pay-back support bankability:

· Initial capital investment of USD 218 million
· Life of Mine EBITDA of USD 2.1 billion, corresponding to an EBITDA-margin
of 68%
· Life of Mine Operating Cash Flow of USD 1.7 billion
· Free Cash Flow the first 10 years of full operations of USD 51 million per
annum
· Pay-back period of 4.4 years from start of production

· Optimized schedule and dual mineral production provide competitive strength:

· Outcropping and geotechnically stable orebody
· Low stripping ratio (waste to ore ratio) of 0.6 in open pit
· High-grade rutile and garnet
· Short distance and gravity supported ore transportation minimize
transportation
· 1st quartile revenue-to-cash cost position for rutile


· Optimized mining plan and scheduling support an initial 39 years Life of
Mine:

· 15 years of open pit mining and high-grade processing, and stockpiling of
medium/low-grade ore
· 19 years underground production
· 6 years production based on stockpiled ore
· Extension of Life of Mine expected based on substantial inferred resources


· All permits granted:

·
· Extraction permits for the whole deposit
· Operational license for open pit and underground mining
· Landowner agreements for open pit, infrastructure, and
process plant areas
· Detailed zoning plan
· Environmental permit


· High environmental and social standards in accordance with IFC Performance
Standards and relevant Equator Principles

Comments from Nordic Mining

CEO Ivar S. Fossum comments:

"The UDFS summarizes significant improvements and de-risking of the Project that
will make it an attractive, long-term investment. The combination of reduced
financing needs and environmental improvements underpins a sustainable project.
Engebø will enable strategic market positions in both titanium and garnet.

The Project will be developed in accordance with high international standards
for environment, health, and safety. We have taken initiatives to strengthen
stakeholder dialogues and to monitor and mitigate environmental effects."

Activities going forward
Dialogues with market partners for rutile and garnet are proceeding towards
finalization of offtake agreements on bankable terms and conditions. Subject to
financing, construction will start in the second half of 2021.

UDFS webcast presentation and Executive Summary
The UDFS will be presented today at 10.00 (CET) followed by a Q&A session.